Weekly Status Report Template (plus Daily Report)

A one-page weekly status report and a daily report template, with RAG status rules, a filled People team example with real numbers, and writing tips.

Sign in with Google below to download the PDF and CSV straight away.

Get your free download

Sign in with Google to unlock the PDF and CSV instantly. No form to fill in.

Free. By continuing you agree to our terms and privacy policy. We record your email and this download; marketing emails only if you tick the box.

What you get

  • A weekly status report layout that fits on one page: summary, metrics, progress, risks, next week
  • A daily report template for shift handovers, field teams and new starters
  • Red/amber/green definitions that stop every project from being 'green until it's red'
  • A filled example for a People team with hiring, onboarding, ER and payroll numbers
  • Blank tables for projects, metrics, risks and decisions needed

Template preview

A preview of the structure. Download the PDF or CSV for the complete, ready-to-use version.

Report header

Team / project
Author
Week covered— e.g. Monday, Sept 21 – Friday, Sept 25, 2026
Overall status— Green / Amber / Red, using the definitions below

RAG status definitions

StatusMeaningWhat the reader should do
GreenOn track for scope, date and budget; no help neededNothing
AmberAt risk: a date, budget or scope target may be missed, but there is a recovery plan the team controlsRead the risk and plan; be ready to help
RedWill miss a committed date, budget or scope without a decision or help from outside the teamAct on the decision requested this week
CompleteDelivered and acceptedNothing

Filled example: People Operations weekly report

Team: People Operations · Author: [Name], HR Manager · Week: Sept 21–25, 2026 · Overall: Amber Summary: Hiring is on track for Q4 (14 of 18 offers accepted). Open enrollment prep is amber because the benefits broker's renewal rates arrived 6 days late; we need a decision on the employee contribution split by Wednesday, Sept 30. One new ER case opened; no escalations.

Key metrics (example)

MetricThis weekLast weekTargetNote
Open requisitions2225< 20 by Oct 313 filled, 0 new
Offers accepted (Q4 to date)141118 by Oct 311 declined (comp)
Median time to fill (days)384135Engineering roles 52 days
New hires started64–All completed I-9 on day 1

Projects and progress (example)

ProjectStatusDone this weekNext weekDue
Q4 hiring planGreen3 offers accepted; panel training for 12 interviewersFinal-round interviews for 4 rolesOct 31
2027 open enrollmentAmberRenewal rates received Sept 24 (due Sept 18)Model 3 contribution options; draft commsNov 2 launch
HRIS time-off moduleGreenUAT with 2 pilot teams; 5 bugs logged, 4 fixedFix last bug; train managersOct 15
Handbook update (state leave laws)RedCounsel review not startedDecision needed: see belowOct 1 (legal effective date)

This is a preview — the full template continues in the download.

Sign in above to download the full template.

How to use this template

  1. 1

    Agree the audience and send time

    Pick who reads it (manager, leadership, a project sponsor) and a fixed send time, for example Friday by 2 p.m. covering Monday to Friday.

  2. 2

    Write the summary last

    Fill in metrics, progress and risks first, then write the three-line summary. A reader who stops after the summary should know the one thing that needs their attention.

  3. 3

    Use RAG status honestly

    Apply the definitions in the template. Amber early is useful; a surprise red is not.

  4. 4

    Ask for decisions explicitly

    List any decision you need, who needs to make it and by when. This is the section leaders act on.

  5. 5

    Keep the same format every week

    Readers scan faster when the layout never changes. Carry open risks forward until they are closed.

Frequently asked questions

What should a weekly report include?

A three-line summary, overall status, the key metrics against target, progress on each project (done this week, next week, due date), risks and issues with owners, and any decisions you need with a deadline. Keep it to one page so readers finish it.

How do you write a weekly status report quickly?

Use the same template every week and update it from your task list or project tool on Friday morning. Fill in metrics and projects first, then write the summary. Most people get it under 20 minutes once the format is fixed.

What is RAG status in a report?

Red, amber, green. Green means on track with no help needed; amber means at risk but the team has a recovery plan; red means a date, budget or scope commitment will be missed without a decision or help from outside the team. Define them in writing so everyone uses them the same way.

What is the difference between a daily and a weekly report?

A daily report records what one person or shift did, what is carrying over and any blockers, and is mainly for handovers and close supervision. A weekly report rolls up progress, metrics and risks for a team or project and asks leaders for decisions.

Who should receive a weekly status report?

Your manager and anyone who needs to act on it: project sponsors, leaders whose decisions you need, and peer teams with dependencies. Keep the distribution list short. People who only need the headline can get the summary lines in a chat channel.